I-70 Floyd Hill to Veterans Memorial Tunnels Design and Construction
Rock Blasting for the I-70 Floyd Hill Project

About the Project
The I-70 Floyd Hill Project, from west of Evergreen to eastern Idaho Springs, encompasses an eight mile section of the I-70 Mountain Corridor that acts as an economic gateway for the state of Colorado and the nation. Home to long-time residents, dozens of large and small businesses and tourism traffic, this section of I-70 is in desperate need of improvements. CDOT spent several years studying the corridor, meeting with residents, stakeholders and community leaders, and drafting potential solutions for this corridor whose aging infrastructure is long overdue for replacement. Now, with support from stakeholders and national leaders, construction of the I-70 Floyd Hill Project is underway and began with its Early Projects.
Project Facts
- Estimated Construction Cost: $700 million
- Contractor: Kraemer North America
- Timeline: Construction is anticipated to begin in June 2023 and be completed in 2028.
- Location: Westbound Interstate 70 from east of the Floyd Hill/Beaver Brook Exit (248) through the Veterans Memorial Tunnels to Colorado Boulevard/Idaho Springs Exit (241)
The I-70 Floyd Hill Project will include:
- Add a third westbound I-70 travel lane in this two-lane bottleneck. This new lane will be a full-time, tolled Express Lane from just west of Homestead Rd. (Exit 247) through the Veterans Memorial Tunnels to Colorado Blvd./Idaho Springs (Exit 241)
- Rebuild bridges due to use, wear and tear, and heavy usage
- Construct a missing two-mile section of the frontage road between US 6 and the Hidden Valley/Central City Parkway interchanges, which will improve emergency response
- Build an extended on-ramp from US 6 onto eastbound I-70 for slow-moving vehicles to have more room to merge
- Improve traffic flow and access at interchanges and intersections
- Improve sight distance and safety by straightening roadway curves
- Improve the Clear Creek Greenway trail
- Implement environmental mitigation to enhance wildlife connectivity, air and water quality, stream conditions and recreation
- Install two permanent air quality monitors
The Project has been designed and will be constructed in three main geographic sections shown on the map below.

three sections - East, Central and West.
Project Benefits:
- Address the bottleneck on I-70 at Floyd Hill and improve travel time reliability.
- Rebuild bridges to today’s safety standards.
- Improve traffic flow and access at interchanges and intersections.
- Improve design speeds and stopping sight distance on horizontal curves.
- Implement environmental mitigation to enhance wildlife connectivity, air and water quality, stream conditions and recreation.
Work Schedule
- Construction is anticipated to last approximately five years
Traffic Impacts
- During construction, motorists can expect:
- Occasional daytime traffic holds during rock blasting and rock scaling operations.
- Overnight lane closures.
- Temporary lane shifts.
- Periodic, temporary on- and off-ramp closures.
- Periodic, overnight detours in the I-70/US 6 interchange and short-term closures of I-70 for safety critical work.
- Temporary closures of the Clear Creek Greenway trail.
- Efforts to keep I-70 moving during construction include:
- Keeping all lanes and ramps open during peak traffic hours.
- Ensuring lane closures are responsive to current traffic patterns.
- Innovating complex work above the roadway so it doesn’t impede traffic.
- New roadway sections are being built adjacent to current lanes to keep traffic moving.
- Promote the use of transit and carpool options to reduce single occupancy vehicles.